Cobb Environmental Projects


Client Facility Start Date Project Duration
Cobb Cheatham Rd. Balefill 1994 Semi-Annual Groundwater Monitoring 2
    1995 Corrective Action Work Plan 1
    2003 Semi-Annual Groundwater Monitoring 7
         
  Co. Farm Dr. 1994 Semi-Annual Groundwater Monitoring 2
    1995 Methane Well Installations 1
    2003 Semi-Annual Groundwater Monitoring 7
         
  Co. Farm Rd. 1994 Semi-Annual Groundwater Monitoring 2
    1995 Methane Well Installations 1
    2003 Semi-Annual Groundwater Monitoring 7
         
Average of Duration       3.3

Environmental Images

This operations building sits at the edge of the closed waste unit behind. To protect site personnel, AEM recommends allowing adequate ventilation under such structures to prevent accumulation of landfill gases in the structure.
This operations building sits at the edge of the closed waste unit behind. To protect site personnel, AEM recommends allowing adequate ventilation under such structures to prevent accumulation of landfill gases in the structure.21-Nov-2006 10:30, SONY DSC-W70, 7.1, 6.3mm, 0.013 sec, ISO 100
 
12-Sep-2003 17:11, SONY CD MAVICA, 2.3, 15.8mm, 0.033 sec, ISO 160