Cobb Environmental Projects


Client Facility Start Date Project Duration
Cobb Cheatham Rd. Balefill 1994 Semi-Annual Groundwater Monitoring 2
    1995 Corrective Action Work Plan 1
    2003 Semi-Annual Groundwater Monitoring 7
         
  Co. Farm Dr. 1994 Semi-Annual Groundwater Monitoring 2
    1995 Methane Well Installations 1
    2003 Semi-Annual Groundwater Monitoring 7
         
  Co. Farm Rd. 1994 Semi-Annual Groundwater Monitoring 2
    1995 Methane Well Installations 1
    2003 Semi-Annual Groundwater Monitoring 7
         
Average of Duration       3.3

Environmental Images

Installation of a Landfill Gas vent trenchInstallation of a Landfill Gas vent trench
Installation of a Landfill Gas vent trench
Soil Vapor Extraction System custom-built by AEMSoil Vapor Extraction System custom-built by AEM
Soil Vapor Extraction System custom-built by AEM